Bags concrete calculator

A bag of dry mix.

How many bags of each size a pour takes, rounded up.

ft
ft
$/yd³

Decimals fine. Bag counts round up.

At 20 × 20 ft and 4 inches you need

4.94 cubic yards

133.3 cubic feet · 18,670 lb of concrete · order 5.43 yd³ with the 10% waste allowance

223bags of 80 lb245 with 10% waste
297bags of 60 lb326 with 10% waste
1mixer-truck load
$830–$1,120ready-mix at $180/yd³

Order ready-mix. At 4.94 yd³ you are 3.7 times past the point where bagging pays. That is one truck, one morning — against 223 bags to lift, mix and place before the first batch sets.

Two rules, each where it applies. Bag counts carry no waste allowance — a partial bag is not a thing you can buy, and an unopened one goes back — so the headline count is the volume and the figure beside it is the same count with waste. The ready-mix figure carries its allowance inside because a truck will not come back for a quarter yard.

Section through the slab. Thickness is measured from the top of the compacted gravel base, not from the ground. 4 inmeasure from herenot from here

The inch that costs $240

Thickness runs from the top of the compacted gravel to the finished surface. Measure from the dirt and you count the base as concrete: on this pour, one inch of that error is 1.23 extra cubic yards — about $240 of ready-mix, or 56 bags nobody needed. Set a stake to the finished height before you order.

The arithmetic, in the open

How this page gets its numbers

Volume, cubic feet
20 × 20 × (4 ÷ 12) = 133.3 ft³
Cubic yards
133.3 ft³ ÷ 27 = 4.94 yd³
80 lb bags
ceiling(133.3 ÷ 0.60 ft³ a bag) = 223 bags, no waste allowance; with 10% waste, 245
60 lb bags
ceiling(133.3 ÷ 0.45 ft³ a bag) = 297 bags, no waste allowance; with 10% waste, 326
Weight
133.3 ft³ × 140 lb per ft³ = 18,670 lb
Order allowance
4.94 yd³ plus 10% = 5.43 yd³ ordered
Truck loads
ceiling(5.43 yd³ ordered ÷ 10 yd³ a load) = 1 — a full truckload is typically about 10 cubic yards

Bag counts round up. A partial bag is not a thing you can buy, so a calculated 222.2 bags is 223 bags.

Bags presets

The 6 sets people ask for most

At 4 in thick; the arrow figure is the same bag count with 10% waste.
SlabArea ft²Cubic yards80 lb bags→ with 10% wasteBuy as
4 × 4 ft 16 0.20 9→10 Bags
6 × 6 ft 36 0.44 20→22 Bags
8 × 8 ft 64 0.79 36→40 Bags
8 × 10 ft 80 0.99 45→49 Bags
10 × 10 ft 100 1.23 56→62 Bags
10 × 12 ft 120 1.48 67→74 Ready-mix

What a bag holds

Every bag size, and what it yields

Yields as published on QUIKRETE Concrete Mix data sheet No. 1101. Bags a yard is 27 ÷ the yield, rounded.
Bag sizeYield ft³Bags a yard
40 lb bag0.30090
50 lb bag0.37572
60 lb bag0.45060
80 lb bag0.60045
90 lb bag0.67540

A different shape

The other 7 calculators

Asked about this shape

Questions

How many bags is that?

223 bags of 80 lb, or 297 of 60 lb, both rounded up and both stated without a waste allowance. With 10% waste they are 245 and 326.

How many 80 lb bags are in a cubic yard?

45, and you buy 45. An 80 lb bag of mix yields about 0.60 cubic feet once water is in it, and a cubic yard is 27 cubic feet. A 60 lb bag yields about 0.45 cubic feet, so 60 of those make a yard. Every bag count on this site is rounded up, because a store will not sell you nine tenths of a bag.

Which bag size should I buy?

The one your store stocks in quantity. An 80 lb bag yields about 0.60 cubic feet and a 60 lb bag about 0.45, so the yards work out the same either way; the difference is how many you lift. Above 60 bags of 80 lb the lifting is the argument for ready-mix, not the price.

Bags or ready-mix — where is the line?

Around 60 bags of 80 lb, which is 36 cubic feet or 1.33 cubic yards. Under that you can mix it in a day with a rented mixer and one helper, and you pay only for what you open. Over it you are buying several pallets, handling two tons or more by hand, and racing the set on the first batch you placed. Some plants charge a short-load fee below about 3 yards, so ask when you book.

How much extra should I order?

10 percent, and where it appears depends on what you are buying. Ready-mix carries it inside the ordered figure, because a truck will not come back for a quarter yard. Bag counts do not: the headline count is the volume, and the plus figure sits beside it, because bags are bought one at a time and an unopened one goes back. Either way the allowance covers spillage, a base that is not perfectly flat and the thickness you gain at the edges of the form.

Does adding more water stretch a bag?

No. The yield printed on the bag is at the water ratio printed beside it. Mixing wetter gives you the same volume of weaker concrete, and a slab that cracks. Every yield on this site is the published one.

Does this include rebar, forms or labour?

No. The price band is concrete delivered: your own price per yard on the ordered volume, taken 15% either side of the middle to cover what a quote actually varies by. Forms, gravel, mesh or bar, a pump if the truck cannot reach, and finishing are all separate. Get the plant to quote your postcode before you budget.

Bag yields: QUIKRETE Concrete Mix data sheet No. 1101. Price basis: Concrete Financial Insights weighted average selling price for 2025, escalated with U.S. Bureau of Labor Statistics PPI series PCU327320327320 (2026-07). Prices vary by region — enter your own quote above.